The West Virginia Division of Highways announces that Hartsook Road will be closed to through traffic according to James F. Moore, District Nine Maintenance Engineer.
Slope stabilization work will begin on CR 9/8, Hartsook Road, on Monday, July 13, at 7:30 a.m. The project is located approximately one quarter of a mile west of the junction with Shoestring Trail. This work will take approximately two weeks to finish and should be completed before Friday, July 24. Hartsook Road will be closed to through traffic between 7:30 a.m. and 5:30 p.m., Monday through Saturday, during this period of time. Local traffic will have access to all properties along Hartsook Road via Cornstalk Road.
Please be advised that inclement weather or unforeseen circumstances may change the work schedule.